Planning appeal guide for 2026: deadlines, the new evidence rule and what to do if planning permission is refused

A planning appeal lets you challenge a council's refusal, a condition you object to, or a failure to decide your application, and in England it is decided by the Planning Inspectorate. The rules changed on 1 April 2026. For most applications made on or after that date, an appeal decided in writing is now judged only on the evidence the council saw at application stage, so what you submit first matters far more than it used to.

When you can make a planning appeal. GOV.UK lists three situations: you were refused planning permission for reasons you think go against the council's development plan or planning policy; you were granted permission with conditions you think are unnecessary, unenforceable, vague, unreasonable or irrelevant; or the council has not decided your application in time. A council normally has 8 weeks to decide a standard application and 13 weeks for major development, such as 10 or more homes, unless you agreed a longer period in writing. Only the person who made the planning application can appeal, and if you do not own the whole site you must notify the owners and any agricultural tenants within the 21 days before you appeal.

Planning appeal deadlines. The Planning Inspectorate must receive your appeal within these time limits. Refused householder application, such as an extension or loft conversion: 12 weeks from the date on the decision notice. Refused minor commercial application: 12 weeks. Advertisement consent: 8 weeks. Most other refusals, including larger residential schemes and listed building consent, and appeals against conditions: 6 months from the decision notice. Failure to decide: 6 months from the date the council should have decided. If an enforcement notice has been served on the same or very similar development, the limit can drop to 28 days, so check that first. If the appeal and its supporting documents arrive late, the Inspectorate will not accept it.

The new evidence rule from 1 April 2026. Under the Town and Country Planning (Appeals) (Written Representations Procedure) (England) (Amendment and Saving Provision) Regulations 2026, appeals against refusals or conditions on applications made on or after 1 April 2026 that are decided by written representations follow the expedited "Part 1" procedure. You send the appeal form, a copy of the application form, the decision notice and, where needed, an environmental statement and a completed planning obligation. The council sends its questionnaire and the application documents. There is no statement of case and no chance to add new evidence the council has not seen, unless there has exceptionally been a material change of circumstance since the decision. Interested people cannot comment again either; the inspector relies on what was said at application stage. The inspector usually visits the site and then issues the decision. Applications made before 1 April 2026 stay under the earlier procedure.

Hearings and inquiries. The Planning Inspectorate can decide that a hearing or an inquiry is more suitable, using its published criteria. You can say on the appeal form which procedure you think is right and why, and the Inspectorate keeps the choice under review. Hearings and inquiries still involve a full statement of case.

How long does a planning appeal take?

For section 78 planning appeals in England decided in September 2026, the Planning Inspectorate's median time from the appeal becoming valid to a decision was 18 weeks for written representations, 24 weeks for hearings and 25 weeks for inquiries. Householder written appeals had a median of 12 weeks.

The same official figures, published on GOV.UK on 22 October 2026, also give a mean of 20 weeks for written representations (669 decisions), 30 weeks for hearings (27 decisions) and 14 weeks for householder written appeals (278 decisions). The inquiry figures, a median and mean of 25 weeks, are based on only 7 decisions, so the Planning Inspectorate says they should be treated with caution.

The times run from the date the Inspectorate was able to progress the appeal, when it became valid, to the date the decision was issued. They are based on appeals that have already been decided, and they are not a target or an estimate of how long a new or current appeal will take.

Planning appeal FAQs

How long does a planning appeal take?

For section 78 planning appeals in England decided in September 2026, the Planning Inspectorate's median time from the appeal becoming valid to a decision was 18 weeks for written representations, 24 weeks for hearings and 25 weeks for inquiries. Householder written appeals had a median of 12 weeks. The inquiry figures are based on only 7 decisions and should be treated with caution. These figures are not a target or an estimate for a new appeal.

Appeal costs. Each side normally pays its own costs. Costs can be awarded against a council or an appellant that behaves unreasonably and so causes the other side unnecessary expense, either on application or at the inspector's own initiative.

Practical steps before and after a refusal. Treat the application as the appeal file: include the technical reports, plans and policy case you would want an inspector to read, and answer consultee objections before the council decides. If you are refused, read the reasons for refusal and the officer's report closely, and diary the deadline on the day the decision notice arrives. Where the refusal turned on missing information, a fresh application with the extra evidence may be quicker than an appeal that cannot consider it; our note on planning application fees rising on 8 December is worth reading if you are weighing that up. For an example of an appeal in Yorkshire, see the Howden permission in principle appeal, and our guide to planning consultants explains when outside help is worth it.

This note is general information only, not legal or compliance advice. Jonathan offers consultancy on gaming and casino licensing, site finding, site planning, planning applications and property feasibility. For introductions, contact Jules at pa@jonathantruelove.com.

For help with a licence, site or planning application, get in touch, or read more about property and planning work.

Sources: GOV.UK, Appeal against a planning decision; Planning Inspectorate, Planning appeals: procedural guide for applications dated on or after 1 April 2026; SI 2026/122, Written Representations Procedure (Amendment and Saving Provision) Regulations 2026; GOV.UK, Simpler, faster planning appeals are coming; GOV.UK, Appeals: how long they take (updated 22 October 2026, September 2026 data)