How long does planning permission last? In England, a full planning permission normally has to be started within three years of the date it is granted, unless the council sets a different period in the decision notice. If work has not lawfully begun by then, the permission expires and a fresh application is needed. The rule comes from section 91 of the Town and Country Planning Act 1990, and it is one of the most common things landowners and buyers get caught out by.
Outline planning permission. Outline permission works differently. Under section 92 of the Act, applications for approval of the reserved matters (details such as layout, scale, appearance and landscaping) must normally be made within three years of the outline grant, and the development must then be begun within two years of the final reserved matters approval. Councils can set longer or shorter periods, and can set separate periods for different phases, so always check the conditions on the decision notice itself.
What counts as starting. Section 56 of the Act says development is begun on the earliest date a "material operation" starts. That includes construction work on a building, demolition of a building, digging a trench for foundations, laying an underground main or pipe to the foundations, and work on laying out or building a road. A token start can be enough in law, as long as it is part of the approved development. Generally, any pre-commencement conditions need to be dealt with first, and starting without discharging them can mean the permission has not been lawfully implemented.
Can the time limit be extended? Not by asking the council to vary it: section 73 of the Act does not allow a permission to be granted that extends the time for starting development or for applying for reserved matters. The main exception is a legal challenge. Since 18 February 2026, changes made by the Planning and Infrastructure Act 2025 mean that if a court gives permission for a legal challenge to a permission in England, the time limit is extended by one year, with further extensions if the case goes to the Court of Appeal or the Supreme Court.
Practical checks. If you are buying land with planning, note the decision date and the expiry date, check which conditions must be met before work starts, and keep dated evidence of the works that count as a start. If there is any doubt about whether a permission was lawfully begun, you can apply to the council for a lawful development certificate to confirm it. With a permission close to expiry, it is often better to plan a properly discharged start early than to rely on a last-minute dig.
How long does temporary planning permission last?
In England, the length is set by a condition on the decision notice. There is no fixed national period. Section 72 of the Town and Country Planning Act 1990 lets a council grant permission for a limited period only. When it ends, the condition normally requires the use to stop or the building or works to be removed.
Planning permission FAQs
Can planning permission be extended?
Not by asking the council to vary it. In England, section 73 of the Town and Country Planning Act 1990 does not allow a permission to be granted that extends the time for starting development or for applying for reserved matters. If time is running out, the usual route is a fresh planning application. The main exception is a legal challenge. Since 18 February 2026, if a court gives permission for a legal challenge to a planning permission in England, any time limit still running is extended by one year. There is a further year if permission to appeal to the Court of Appeal is given, and two more years for the Supreme Court.
What counts as starting work?
Section 56 of the Town and Country Planning Act 1990 says development is begun on the earliest date a material operation starts. That includes construction work on a building, demolition of a building, digging a trench for foundations, laying an underground main or pipe to the foundations, and work on laying out or building a road. A token start can be enough in law, as long as it is part of the approved development. Pre-commencement conditions generally need to be dealt with first, and starting without discharging them can mean the permission has not been lawfully implemented.
What are the time limits for outline planning permission?
Under section 92 of the Town and Country Planning Act 1990, applications for approval of the reserved matters, such as layout, scale, appearance and landscaping, must normally be made within three years of the outline grant. The development must then be begun within two years of the final reserved matters approval. Councils can set longer or shorter periods, and can set separate periods for different phases, so always check the conditions on the decision notice.
If you need help with a permission that is close to expiry, or with a start on site, book a call.
This note is general information only, not legal or compliance advice. Jonathan offers consultancy on gaming and casino licensing, site finding, site planning, planning applications and property feasibility. For introductions, contact Jules at pa@jonathantruelove.com.
Need help with a licence, site or planning application? Get in touch.
Sources: Town and Country Planning Act 1990, section 91; section 92; section 56; section 72; section 73 (legislation.gov.uk); GOV.UK, Use of planning conditions (planning practice guidance)